Shortly before the start of operation
|
|
|
|
|
|
|
|
|
|
|
Start of operation: Spring 2009
Processing capacity: 1,000 Nm³/h of raw biogas
Input: NAWARO
On order by the regional utility company E.ON Mitte AG and C4 Energie
AG, the companies MT-Energie GmbH & Co. KG and MT-Biomethan GmbH
are currently building a complete biogas project with a fermentation
line and gas processing system in Hardegsen, Germany (county of
Northeim). This large-scale project has a total volume of approximately
eleven million euros.
In all the new biogas plant comprises seven tanks – two digesters, two
post-digesters and three residue storage tanks. From the spring of 2009
it will produce 35,315 cu ft (1,000 m3) of raw biogas per hour. More
than 40 farms from the region supply the raw materials required to
operate the plant.
The biogas plant serves as a pilot project for the processing of biogas
in Lower Saxony. E.ON Mitte will buy the raw biogas produced from
Hardegsen C4 Energie GmbH& Co. KG, process it to natural gas
quality and feed it into the general gas network.
C4 Energie
|
|